ARTIFICIALJournal

Construction15 min read

Scheduling work on site: the art of trades that do not wait for one another

The most expensive thing on a building site is not cement or labour; it is waiting. The painter waits for the plaster to dry, the tiler for the plumber, and everyone for the material that has not arrived. A good programme of works sees these waits in advance and places work between them. This article explains how that programme is built, what is done when it rains, and what changes between the refurbishment of a flat and the construction of a building.

Alp Diker · Interior Architect, M.A.

01Where did this idea come from? Bars, networks and a skyscraper

The bar chart we call a programme of works spread in the 1910s under the name of the American engineer Henry Gantt. It was the period in which work was measured with a stopwatch in factories and efficiency had become almost a belief. Gantt’s chart made a simple thing visible: which task begins when, when it ends, and where we are today.

The most famous site showing what the method can do is in New York. The Empire State Building rose in 1930–31, after the demolition of an old hotel, in 410 days. The steel frame advanced by about four and a half storeys a week; up to 3,400 workers a day were on the site. The secret was that the work was set up like an assembly line: the steel came from the factory in sequence and went up to its place without waiting in a store, because in the middle of Manhattan there was nowhere to keep material waiting. The constraint gave birth to the method. It had its price too: during construction at least five workers sadly lost their lives. And one more lesson: the building opened in the middle of the Great Depression and stayed half empty for years. Managing a site flawlessly does not mean that the building was built at the right time.

The second great step was taken in the Cold War. In 1957 two engineers, from a chemical company and a computer company, developed the critical path method to plan large maintenance works. Immediately afterwards the American navy set up a similar network method for a missile programme on which thousands of contractors worked. Both asked the same question: if which of these tasks is late will the whole project be late? The computer was needed for the method to appear, because the links between thousands of tasks could not be calculated by hand. In the 1970s more than four fifths of America’s large construction firms were using this method.

The third step is more modest and, in my view, the most important. In the 1990s two researchers followed weekly plans on sites one by one and found something uncomfortable: a considerable part of the tasks declared at the start of the week as “to be done this week” had not been done by its end. The problem was not in the large programme; it was on Monday morning. We return to this below.

02What is a programme of works really for?

A good programme answers three questions. Which task is waiting for which? Which material must be ordered when? If something goes wrong, what can I move and what can I not? The chart looking well on the wall provides none of these three.

The value of a programme is measured in money. A team coming to site and going back without finding work means that day’s wages. Work done in the wrong order is work done twice: a services chase opened after painting calls back both the plasterer and the painter. A late handover returns as rent, interest and reputation. The figures for these are the subject of a separate article on the cost of cheap construction; here we look at how it is prevented.

03The golden rule: wet trades first, dry trades after, dusty work first of all

The sequence of an interior site is not arbitrary; physics sets it. Every task that contains water (plaster, screed, gypsum, tile adhesive) needs to dry, and until it dries it spoils the work that comes on top of it. Every task that raises dust is the enemy of a finished surface. Three rules follow:

The item most often forgotten is drying time, because on the chart it does not look like “work”. For cement-based screed the common rule is this: for the first 4 cm, roughly one week for every centimetre. To lay timber on a screed of 5 cm it is necessary to wait more than a month. If this time is not written into the programme as an item of work, the parquet is laid on damp screed and lifts in the first winter.

12345678 Strip-out, chasing Services, electrics Plaster, gypsum Screed Drying Tiling Suspended ceiling Paint, first coats Kitchen, joinery Parquet Final coat, fittings Columns are weeks. Yellow is waiting, not work; yet it is the longest item.
FIGURE 1A sample programme for the refurbishment of a medium-sized flat. While the screed dries the site does not stand empty: tiling, the suspended ceiling and the first coats of paint are placed in that interval. Parquet does not begin before drying is complete. The durations are examples; each job is calculated from its own survey.

04The critical path: which delay delays everyone?

When you link the tasks to one another with arrows, a network emerges. In this network the longest chain from start to finish is called the critical path. If a task in that chain is one day late, the handover is one day late too. The tasks outside the chain, by contrast, have a margin: if they slip a few days the handover is not affected. This margin is called float.

Strip-outServicesScreed + dryingParquetKitchen order 1 week1.5 weeks5 weeks0.5 week Thick frame: critical pathThin frame: a task with float. Started early it keepsno one waiting; started late it keeps everyone waiting.
FIGURE 2A simplified network. What sets the handover is the tasks that cannot be shortened, such as the drying of the screed. The kitchen order has float, but that float ends on the day the order is placed late.

A manager’s attention is limited, and the critical path says where that attention is to be spent. The task on the critical path is given the best team, the earliest material and daily checking. In tasks with float, flexibility is a resource: on a rainy day, or on a morning when a team has not come, the next task is drawn from there.

A warning: as float is spent, the critical path moves. If the kitchen order, with three weeks of float, is forgotten for three weeks, it is now the most critical task of the project. On sites that make the programme once and hang it on the wall, delay generally comes from here.

05Planning backwards: first the order, then the pickaxe

Sites are very often late not because of labour but because of material. The remedy is to read the programme in reverse: subtract the lead time from the day of installation and you have the day of the order; subtract from that the time for deciding and measuring and you have the day of selection.

Made-to-order furniture6–8 weeks Natural stone, special tiles4–6 weeks Windows, doors, glass3–5 weeks Imported fittings, lighting4–8 weeks Bar: time from order to delivery. Selection and measuring are added to it.
FIGURE 3Approximate times for long-lead items. These vary with the market, the season and the product; for each job a written lead time is obtained from the supplier. The rule does not change: the decision on the item with the longest lead time is taken before the site begins.

A duty for the owner follows from this too. If the colour of the tiles is to be chosen after the screed has been laid, the programme is already late. In a well-managed job the decisions have a calendar as well, and this calendar is signed together with the client. Indecision is the most expensive material on site.

06The weather: how does the programme follow the sky?

The weather is the one partner on site with whom there is no bargaining. One does not plan against it; one plans with it. The way to do so is always to keep in hand a list of “inside work” and a list of “outside work”; when the weather turns the team is not left idle, and the list changes.

WeatherWork to postponeWork to bring forwardWhy
RainExternal painting and rendering, roof waterproofing, concrete pours, excavationInternal services, electrics, plasterboard, workshop fabricationWaterproofing does not bond to a wet surface; fresh render and paint are washed off
Frost and below +5 °CConcrete, screed, plaster, tiling, external paintingStrip-out, dry systems, mechanical installationCement cannot gain strength in the cold; water that freezes cracks the mortar from within
Extreme heat and dry windConcrete and plaster at middayThe same work early in the morning or in the evening; inside work during the dayWater evaporates quickly and the surface cracks; watering and covering are needed
Strong windCrane work, work on scaffolding, façade cladding, roofGround floor and inside workSafety; there is no bargaining over it
High humidityTimber flooring, final coat of paint, varnishRough work, installationTimber takes up moisture and then shrinks; paint dries late and leaves marks

The season also sets the skeleton of the programme. In a city with a hard winter such as Ankara, the concrete work of the structure is finished, if possible, before the frost arrives; if the building enters winter closed, work continues inside. To begin interior finishes before the roof and façade are closed is to invite the rain onto the site. In interior refurbishment the weather is less decisive, but it cannot be ignored: in an unheated flat in winter the screed does not dry for weeks, and in a flat without air conditioning in summer the paint dries too fast and leaves roller marks.

So that is why

Why do craftsmen say “let the weather clear, then we will pour”? Concrete hardens by a chemical reaction, and this reaction slows in the cold and almost stops as it nears freezing point. If the water inside it freezes at that time it expands and breaks apart, from within, concrete that has not yet gained strength. Concrete can be poured in winter, but it asks for heating, covering and admixtures; all of these mean money and a place in the programme. The craftsman’s sentence is not idleness; it is chemistry.

07The Monday morning problem: the weekly plan

The large programme looks at months; the site lives by days. What the two researchers found on sites in the 1990s was this: most delays came not from large errors of calculation but from weekly promises not being kept. The reasons were always the same: the drawing had not arrived, the material had not arrived, the previous team had not cleared the area, the scaffolding had not been erected, the priority had changed.

The remedy they proposed is plain and works at every scale:

Before60% After87% On one sample site: share of the week’s planned tasks finished that week.
FIGURE 4An example reported by the researchers who developed the method. The difference does not come from working faster; it comes only from promising work that is ready.

There is a psychological side here too. A team working to a programme in which it can keep its word trusts the programme and prepares accordingly. In a programme that breaks down every week, everyone hides their own margin: the craftsman says five days for work he would call three, the manager does not believe this and writes two, and the chart turns into a piece of paper nobody takes seriously.

08Scale 1: the refurbishment of a flat or an office

The particular difficulty of refurbishment is that the building is alive. The neighbours, the working hours in the building’s management plan, the lift, the car park, the removal of rubble: all of these are part of the programme, and most are forgotten in the first chart.

PHOTOGRAPHAn old building under scaffolding. In repair the scaffolding is not only a working platform but the programme itself: its hire begins to run on the day it is erected, and all the work on the façade has to fit within its period.ell brown · CC BY 2.0 · Flickr

09Scale 2: the construction of a new building

At the scale of construction the rules are the same, but two things change: the weather becomes decisive, and repeated work gains a rhythm.

PHOTOGRAPHBefore the concrete pour: timber formwork and the reinforcement tied inside it. If openings for services are not left at this stage, the concrete has to be drilled later.MTA C&D - EAST SIDE ACCESS · CC BY 2.0 · Flickr

10Moments of decision: speed up or wait?

SituationWhat looks attractiveThe right course
The work is late and handover is approachingPutting more craftsmen on every taskAdding resources only to the task on the critical path; a craftsman added to the others does not bring the handover forward
The screed has not yet driedLaying the parquet and finishing the jobMeasuring the moisture; if necessary speeding the drying with heating and dehumidification
Material is lateKeeping the team waitingBringing forward another task that has float; if there is none, releasing the team and giving a new date
The client asks for a changeSaying “we will sort it out”Writing down the effect of the change on time and cost, obtaining approval, and then starting
A team has finished earlyCalling the next team immediatelyChecking the work first; work that comes on top of defective work buries the defect

Overtime and a crowded team gain less than is supposed. A team doubled in a narrow area does not produce twice the work; a tired team makes mistakes, and correcting the mistake takes back the day that was gained. The inexpensive way to speed up is almost always not to work more but to reduce waiting.

11What did it bring, what did it take away?

Planning methods brought foresight to the site: the speed of the Empire State is the proof of the idea of sequenced delivery and the floor cycle, applied today even on an ordinary housing site. The critical path taught where attention is to be spent. The weekly plan method, for its part, brought the craftsman’s knowledge to the table.

There are things they took away too. Computer programs produce handsome charts, and a handsome chart easily takes the place of reality. A programme of thousands of lines can turn into a document nobody on site reads. The price of the passion for speed is clear as well: the record sites of the last century rose in safety conditions that would not be accepted today. Good management is not fast management; it is management that flows. A site that flows looks calm, because nobody runs and nobody waits.

What we have seen since 2014 on factory, office, restaurant, hospital and housing sites is always the same: the jobs that go best are not those on which the most work is done but those that are best sequenced. The programme is not a piece of paper; it is a promise given anew every Monday.

Sources · 3

Next articleFrom Braun to Casio: how did the everyday tool become a design object?Previous articleVinyl tile, glass block, laminate: where did the star materials of an era go?AllAll articles